A Section 106 bond is a form of financial security used to support obligations arising from a planning agreement. It may be required where a developer has agreed to deliver infrastructure, affordable housing, public realm works or financial contributions as part of a development proposal.
The bond is separate from the Section 106 agreement itself. The agreement creates the legal planning obligation. The bond provides a financial guarantee that can be called upon if the relevant obligation is not delivered in accordance with the agreed terms.
Section 106 bonds can be relevant on residential and mixed-use schemes where obligations involve material value, phased delivery or several trigger points. The bond structure should align with the planning agreement, development programme and contractual arrangements for delivering the obligation.
For a wider overview of surety arrangements, read construction bonds explained.
What are Section 106 agreements?
Section 106 agreements are planning obligations entered into under Section 106 of the Town and Country Planning Act 1990. They can restrict the use or development of land, require specified works or activities or require financial contributions to a local planning authority.
The agreement identifies the obligations to be delivered, the relevant trigger dates and how compliance will be evidenced. Triggers may be linked to commencement, occupation, completion of a phase or another event defined in the agreement. Government guidance states that the requirements and timing of obligations should be clear enough to make them enforceable.
Planning obligations are project-specific. Their content will reflect the development, planning policy and negotiations with the local authority. Appropriate planning and legal advice should be obtained before the agreement is finalised.
What is a Section 106 bond?
A Section 106 bond is a financial guarantee that supports a developer’s obligations under a planning agreement. The requirement for a bond is usually set out in the Section 106 agreement itself, often as an obligation to provide the bond before commencement or before a specified trigger is reached. The local authority will normally agree the surety and form of bond before the agreement is completed.
The bond may secure infrastructure, affordable housing or financial contributions. It provides the local authority with financial security if the defined obligation is not met, subject to the bond wording and agreed call conditions.
The bond does not replace the planning agreement or change the developer’s underlying obligations. The agreement remains the legal instrument that defines the obligation, delivery dates and enforcement rights. The bond should reflect the relevant terms of the agreement.
Section 106 bonds are arranged by LBB for residential and mixed-use developers across England and Wales. LBB can advise on bond wording at the planning stage so that it aligns with the planning agreement and proposed delivery timetable.
Typical obligations secured by Section 106 bonds
The obligations secured by a bond vary between schemes. They may include:
- Affordable housing delivery or related contributions
- Public open space, landscaping or play provision
- Infrastructure contributions associated with highways, access or transport improvements
- Education, healthcare or other community infrastructure contributions
- Public realm works or local facilities
Highways works themselves are commonly secured through separate agreements under Section 38 or Section 278 of the Highways Act 1980, with their own bond or security requirements. Where highways works form part of the wider development obligations, the relationship between the Section 106 agreement and any separate highways agreement should be established at the planning stage.
How Section 106 bonds are sized and structured
Bond value is usually tied to the estimated cost of delivering the relevant planning obligation. This may relate to the value of infrastructure works, affordable housing contributions or another defined commitment under the planning agreement.
The value should be reviewed if costs change significantly. A bond based on an outdated estimate may not provide the intended level of security. It may also retain an unnecessarily high value after the developer’s exposure has reduced.
The bond duration and call conditions should reflect the timing of delivery. Section 106 obligations can be triggered at different points in the programme, so the bond period should align with the relevant obligation rather than a generic construction timetable.
Release conditions should be clear, measurable and agreed during the planning stage. Release may depend on completion of works, payment of a contribution or written confirmation from the local authority. Unclear terms can cause disputes and delay the return of security once the obligation has been met.
The difference between the agreement and the bond
The Section 106 agreement is the legal planning obligation. It identifies the land, relevant parties, obligations and triggers. Government guidance states that it must also identify the planning authority that can enforce it and set out the requirements imposed in sufficient detail to be enforceable.
The Section 106 bond is the separate financial guarantee supporting a specified obligation within that agreement. It does not create the planning obligation. Its function is to provide security if the developer does not deliver the obligation in accordance with the agreed terms.
This distinction is important when reviewing bond wording. The secured obligation, bond value, expiry date and call conditions should be consistent with the planning agreement. Any amendment to the agreement may require a corresponding change to the related bond.
What triggers bond release?
A Section 106 bond may be released when the obligation has been delivered or when the local authority confirms that the requirement has been discharged. The precise mechanism should be set out in the planning agreement and bond wording.
Release may be linked to completion of infrastructure works, transfer of affordable housing, payment of a contribution or the expiry of an agreed period where no call has been made. Practical completion of the wider development does not automatically release the bond. The obligation may be linked to occupation, a later phase or another milestone.
Where the bond reduces as obligations are discharged, the documents should state how the reduction is calculated and what evidence the local authority requires. This can prevent security from remaining at its original value after part of the obligation has been fulfilled.
What happens if obligations are not delivered?
If a developer fails to meet an obligation, the local authority may enforce the Section 106 agreement. The consequences will depend on the agreement, nature of the breach and applicable planning framework.
Where a bond is in place, the local authority may seek to call on it if the stated conditions have been met. Whether payment is due depends on the bond wording and the facts of the case. Legal advice should be sought where enforcement action, a proposed call or a dispute about release conditions arises.
The bond is not an alternative to delivering the obligation. It provides financial security for the local authority while the developer remains responsible for meeting its planning commitments.
How LBB arranges Section 106 bonds
LBB arranges Section 106 bonds for residential and mixed-use developments. The process begins with a review of the planning agreement, the obligation to be secured and the proposed delivery or payment timetable.
LBB then approaches appropriate surety markets and assesses available options against the bond value, duration, wording and release conditions. Section 106 bonds can involve multiple triggers, requiring coordination with planning authorities and legal advisers.
A Section 106 bond should also be considered alongside the project’s other security arrangements. It secures planning obligations, while a retention bond may replace cash retention under a construction contract. Read retention bond vs retention clause for an explanation of these different mechanisms.
Speak with LBB to explore appropriate Section 106 bond arrangements for your development.